Registration of New Consumers
The fee for connecting a new facility to the distribution network at the voltage of 0.220 kV, 0.380 kV and 6-10 kV The fee for connecting a new 0.4 kV and 6/10 kV facility to the distribution network according to the offered package: In case of ensuring the connection of the new object to the distribution network within the specified period:
When requesting the joint connection of two or more new facilities, the fee for connecting the new facility to the distribution network is determined by adding the fee for the package offered for the arrangement of a smart meter specified in Appendix No. 4 to the fee provided for in the first paragraph of this article.
Terms and fees for setting up the accounting node
List of multifunction electronic meters:
The meters are included in the register of types of measuring instruments legalized in Georgia, certificate No. 005-16-TR, 23.05.2016. and certificate No. 009-16-TR, 10.10.2016 According to the decision N16/1 of the National Energy and Water Supply Regulatory Commission of Georgia dated April 15, 2022:
According to the decision No. 8/11 of the National Energy and Water Supply Regulatory Commission of Georgia dated February 23, 2023:
National Energy and Water Supply Regulatory Commission of Georgia decision No. 10/2 of March 2, 2023 approved:
contact information:
Bank account: JSC "Basisbank" Bank code: CBASGE22 Settlement Account:GE87BS0000000033836853 Name of recipient: JSC "Telasi" Purpose: fee for connecting a new customer to the distribution network Attached files: