The fee for connecting a new facility to the distribution network at the voltage of 0.220 kV, 0.380 kV and 6-10 kV The fee for connecting a new 0.4 kV and 6/10 kV facility to the distribution network according to the offered package: In case of ensuring the connection of the new object to the distribution network within the specified period:

When requesting the joint connection of two or more new facilities, the fee for connecting the new facility to the distribution network is determined by adding the fee for the package offered for the arrangement of a smart meter specified in Appendix No. 4 to the fee provided for in the first paragraph of this article.

Terms and fees for setting up the accounting node

List of multifunction electronic meters:

  1. CE308 S34.746.OG.QYUVLFZ GS01 - 5(100) A, 3x230/400V, 50Hz, three-phase electronic meter, accuracy class 1.
  2. CE208 S7.846.2.OG.QYUVFLZ GS01 - 5(100) A, 3x230V, 50Hz, single-phase electronic meter, accuracy class 1.

The meters are included in the register of types of measuring instruments legalized in Georgia, certificate No. 005-16-TR, 23.05.2016. and certificate No. 009-16-TR, 10.10.2016 According to the decision N16/1 of the National Energy and Water Supply Regulatory Commission of Georgia dated April 15, 2022:

file
file
file
file
file
file
file
file
file
file
file
file

According to the decision No. 8/11 of the National Energy and Water Supply Regulatory Commission of Georgia dated February 23, 2023:

file
file

National Energy and Water Supply Regulatory Commission of Georgia decision No. 10/2 of March 2, 2023 approved:

file
file

contact information:

  • Regarding electronically and manually filled documents, contact us at the number: 277 99 99 (ext. 7890)

Bank account: JSC "Basisbank" Bank code: CBASGE22 Settlement Account:GE87BS0000000033836853 Name of recipient: JSC "Telasi" Purpose: fee for connecting a new customer to the distribution network Attached files: