New two or more users
The connection of two or more new users to the distribution network refers to the case when, as a result of the construction of a residential apartment, enterprise or other object, two or more new objects (new object's electric network) are connected to the distribution network.
In order to become a JSC Telasi customer, you must fill out an application form and attach necessary documents. For this purpose, the Company offers you to choose the most acceptable and comfortable option from the below listed:
A list of required documentation to receive full service:
Articles 17 and 18 of Semek Resolution N19 of June 28, 2021 regulate the procedures for connecting two or more new customers to the distribution network. And the application form for this connection is: "Requesting connection of two or more new objects to the distribution network".
Two or more new customers Sub-section 1.2 is calculated in the same way as 1.1 and to the resulting fee is added the smart meter installation fee specified in Annex 4 (column #5) for each customer.
Terms and fees for setting up the accounting node
List of multifunction electronic meters:
The meters are included in the register of types of measuring instruments legalized in Georgia, certificate No. 005-16-TR, 23.05.2016. and certificate No. 009-16-TR, 10.10.2016
According to the decision N16/1 of the National Energy and Water Supply Regulatory Commission of Georgia dated April 15, 2022: